What kind of relationship exists between these two activities?

Activity A has ES-5, EF-10 and Activity B has ES-7, and the duration is 4 days. What

 

kind of relationship exists between these two activities?

 

(a)     Finish to Start

(b)     Finish to Finish

(c)     Start to Finish

(d)      Start to Start

Question: 292

Your project is 90% completed, the cost performance index is 1.2 and the schedule performance index is 0.8. Management is concerned about the delay and asks you to utilize schedule compression so the project can be completed on time. Which of the following statements is true about the schedule performance index?

 

(a)      SPI will be 1 when the project completes

(b)     SPI will be less than 1 when the project completes

(c)      SPI will be greater than 1 when the project completes

(d)      None of the above

 

find the cost of your paper

Write a program that reads the name of an element from the user and uses a recursive function to find the longest sequence of elements that begins with that value

Some people like to play a game that constructs a sequence of chemical elements where each element in the sequence begins with the last letter of its predecessor. For example,….

What is the correct charge to the income statement for bad debts and bad debt provisions for the years to 31 December 20X1?

Trade receivables as at 31 December 20X1 were $25,000. The bad debt provision as at 1 January 20X1 was $812. During the year to 31 December 20X1 bad debts of….

Which of the following is an adjusting event?

IAS 10 – Events after the balance sheet date, distinguishes between adjusting and non-adjusting events. Which of the following is an adjusting event? (A) One month after the year end,….